A painting estimate example, worked from the drawings.
This walks through a commercial interior repaint-and-new-work estimate the way a painting estimator builds it: quantities by surface and finish code, primer and finish coats, production rates, gallons from the product data sheet, labor, sundries, equipment, then overhead and profit. The rates are illustrative. Swap in your own; the method holds.
Send one plan set. See what the AI extracts and what it flags for review. No obligation.
- Quantities by surface
- Production-rate labor
- Full worked example

The method in one line
For every surface type:
labor hours = area × coats ÷ production rate per coat
gallons = area × coats ÷ spread rate × (1 + loss)
Then add prep, sundries, equipment, supervision, overhead and profit. The skill is in splitting surfaces finely enough that each gets the right rate. Walls under 10 ft rolled in an empty space and stairwell walls at 22 ft cut around rails are not the same line item.
Step 1: Read before you measure
The finish schedule tells you where. The painting spec (usually 09 91 00, with 09 96 00 for high-performance coatings) tells you what. Before measuring, write down:
- Systems by finish code: primer and number of finish coats for each substrate (new drywall, existing painted drywall, CMU, hollow metal, wood).
- Sheen and product requirements, including any named manufacturer or MPI-type requirement.
- Gypsum board finish level. Under the Gypsum Association's GA-214 (2026 edition), Level 4 is typical for flat and eggshell finishes; Level 5 (a skim coat) is recommended for gloss, semi-gloss, dark colors and critical lighting. Level 5 is normally the drywall finisher's work. If the drawings call for semi-gloss on long corridors with Level 4, that's a quality risk to raise, not something to absorb.
- What's excluded or by others: factory-finished items, wallcovering, caulking, exposed MEP.
Step 2: Take off surfaces by type
From the finish schedule, floor plans, reflected ceiling plans and elevations:
- Walls by finish code and height band, in square feet: perimeter × height, deducting only large openings. Many estimators don't deduct doors and windows under about 30 to 40 sq ft, treating the cut-in time as offsetting the area. Pick a rule and use it every time.
- Ceilings in square feet from the RCP, split by gypsum, exposed structure and soffits.
- Doors and frames by count from the door schedule, both sides, with the frame type.
- Trim, base and handrails in linear feet if painted.
- Specialty: exposed structure and deck, piping and ductwork if called for, stair stringers and rails, high walls needing lifts.
Step 3: Worked example quantities and labor
A 7,500 sq ft office build-out with new drywall, 9 ft ceilings, 24 doors (illustrative numbers):
| Surface | Quantity | Coats | Rate per coat | Labor hrs |
|---|---|---|---|---|
| Walls, prime (new drywall) | 9,600 sq ft | 1 | 225 sq ft/hr | 42.7 |
| Walls, eggshell P1 | 9,600 sq ft | 2 | 200 sq ft/hr | 96.0 |
| Gyp ceilings, flat | 1,800 sq ft | 2 | 150 sq ft/hr | 24.0 |
| Doors + frames, both sides | 24 ea | all | 1.5 hr/ea | 36.0 |
| Prep and protection | 11,400 sq ft | — | 0.2 hr/100 sq ft | 22.8 |
| Total | 221.5 |
Production rates are editable illustrative assumptions for rolled and brushed work. Use your crews' tracked rates. Spraying an empty space is much faster per coat but adds masking time. A height band above about 12 ft, occupied space or night work lowers production.
Step 4: Paint quantity from the data sheet
Spread rates come from the product data sheet at the recommended film thickness. Sherwin-Williams ProMar 200 Zero VOC eggshell, for example, lists 350 to 400 sq ft per gallon at 4 mils wet (1.7 mils dry). New drywall absorbs more, which is why the primer is a separate product with its own rate.
Primer 9,600 × 1 ÷ 300 × 1.05 ≈ 34 gal
Walls P1 9,600 × 2 ÷ 375 × 1.05 ≈ 54 gal
Ceilings 1,800 × 2 ÷ 375 × 1.05 ≈ 11 gal
Doors 24 doors + frames ≈ 0.5 gal each ≈ 12 gal enamel
Use the low end of the data-sheet range on textured, porous or rough surfaces, and add coats for big color changes (or a tinted primer).
Step 5: Price it
Illustrative unit costs:
| Item | Calculation | Cost |
|---|---|---|
| Labor | 221.5 hrs × $55/hr burdened | $12,183 |
| Primer | 34 gal × $24 | $816 |
| Finish, walls | 54 gal × $38 | $2,052 |
| Finish, ceilings | 11 gal × $30 | $330 |
| Enamel, doors | 12 gal × $55 | $660 |
| Sundries | 12% of paint (tape, plastic, caulk, covers, masking) | $463 |
| Equipment | Ladders and baker scaffolds only at 9 ft | $0 |
| Direct cost | $16,504 |
Then overhead and profit, and this is where painting contractors most often lose money: markup and margin aren't the same thing.
Overhead 15% markup: 16,504 × 1.15 = 18,980
Profit 10% markup: 18,980 × 1.10 = 20,878 → profit is 9.1% of price
Profit 10% margin: 18,980 ÷ 0.90 = 21,089 → profit is 10.0% of price
On a $20,000 job the difference is about $200. On a $2 million year, it's real money. Decide which one your company means by "10%," and build your spreadsheet to match.
Step 6: Sanity check
- Price per square foot of wall: $20,878 ÷ 9,600 ≈ $2.17. Compare with similar completed jobs in your market.
- Hours per 1,000 sq ft of wall (all coats): (42.7 + 96.0) ÷ 9.6 ≈ 14.4.
- Hours per door: 1.5, all coats.
- Gallons: check coats and spread rates by system.
A big difference from history usually means a rate, quantity or scope assumption is off, not that the market changed overnight.
Scope items people forget
- Exposed structure, deck and ductwork in open ceilings.
- Hollow metal frames in masonry walls, and frames shipped only primed.
- Stairwells: high walls, rails, stringers and soffits.
- Touch-up after other trades and the punch list. Many estimators carry a percentage of labor or a fixed number of crew-days.
- Mobilizations. If the GC's schedule has you in five separate times, price five.
- Coatings listed outside 09 91 00: floor sealers, line striping, intumescent fireproofing, epoxy.
Exclusions to state
Typical painting exclusions include painting of equipment, piping and conduit not called for, factory-finished items, wallcovering, caulking by others, Level 5 gypsum finishing, and repairs to substrates damaged by others. State each one that applies, and match them against the bid form.
Where RenderDraw fits
The slowest part of the example above is Step 2. RenderDraw's AI takeoff proposes wall areas, ceiling areas and door counts from drawings, with the source sheet on every row and uncertain items in a review queue. Your systems, production rates and pricing stay yours.
Where RenderDraw fits: the counting, with your review.
Speed is easy to promise. Defensible numbers are the job, so RenderDraw keeps the estimator in control of every quantity that gets priced.
- Source on every row. Each quantity keeps its source sheet, location and reviewer decision.
- Lowest confidence first. The review queue shows the drawing tile with the detection highlighted and the extracted value.
- Uncertain items flagged, not hidden. Anything the AI can't confirm goes to the estimator rather than being guessed.
- Nothing priced before approval. Rows move on to pricing only after they are accepted.

Questions estimators ask
How do you estimate painting work?
Take off surfaces by type and finish code, apply coats and production rates for labor, spread rates from the product data sheet for material, then add prep, sundries, equipment, supervision, overhead and profit. Split surfaces finely enough that each gets the right rate.
What production rate should I use for painting?
Your own tracked rates by surface, method (brush, roll, spray) and height. Published references like the PDCA Cost and Estimating Guide Volume II (rates and tables) are a starting point, not a substitute for job-cost history.
How many square feet does a gallon of paint cover?
Use the product data sheet. Many interior latex finishes list about 350 to 400 sq ft per gallon at the recommended wet film thickness (for example, Sherwin-Williams ProMar 200 Zero VOC lists 350 to 400 at 4 mils wet). Porous new drywall, texture and dark color changes reduce coverage.
What's the difference between markup and margin?
Markup is a percentage added to cost; margin is a percentage of the selling price. A 25% markup gives a 20% margin. Mixing them up is one of the most common ways painting contractors underprice.
How do I check my painting estimate?
Compare price per square foot of wall, hours per 1,000 sq ft and hours per door with similar completed jobs, and check gallons against spread rates and coats.
Can RenderDraw do the painting takeoff?
RenderDraw's AI takeoff proposes wall and ceiling areas and door counts from drawings, linked to the source sheet for review. Your production rates and pricing stay yours. Request a free sample takeoff.
See what the AI reads on your own drawings.
Send one representative painting plan set. RenderDraw reviews it and follows up with what the AI extracted and what it flagged for review. Your files remain private while the request is assessed, and there is no obligation.
- Upload floor plans, reflected ceiling plans, the room finish schedule, the door schedule and the Division 09 painting/coatings spec.
- RenderDraw reviews the set and the scope you want tested.
- We follow up with extracted quantities, flagged items and next steps.
Related tools and guides
Keep reading on renderdraw.com
Sources and further reading
- Sherwin-Williams ProMar 200 Zero VOC Interior Latex: product data sheet
- PDCA Cost and Estimating Guide, Volume II: Rates and Tables (Google Books)
- Painting Contractors Association (PCA, formerly PDCA)
- Gypsum Association: GA-214-2026 Levels of Finish for Gypsum Panel Products
Figures marked as rules of thumb are starting points, not standards. Check the current edition of any code or standard your project specifies, and use your own historical production rates where you have them. Sources checked 2026-11-01.