Board, mud, tape and screws per square foot come from USG's published rates. Labor comes from your crew. Add burden, overhead and profit and the calculator shows the sell price per square foot and where the money goes.

  • USG material rates
  • Crew production
  • Burdened labor
  • Sell price per square foot
Drywall cost per square foot (hang & finish)

1 · Quantity

2 · Material per sq ft Example values: replace with your quotes

3 · Labor & equipment

4 · Markup

Every default here is an example input, not a market price: material prices, production rates, wages and markups vary by region, job and contractor. Finishing material rates per the USG Gypsum Construction Handbook / J371 guide. Overhead and profit are applied as markups on cost (profit on cost + overhead), which is why "profit as % of price" is lower than the profit %.

Price per sq ft
0 $ / sq ft
sell price incl. overhead & profit
Total price
0
$
Direct cost
0
$ / sq ft
Material
0
$ / sq ft
Labor (burdened)
0
$ / sq ft
Labor hours
0
worker-hrs
Duration
0
crew-days
Profit as % of price
0
%

Where the price goes

Live formula

Save your results

Copy these results, then add your approved sample files in the trial brief.

What goes into it

Material is the small part

On commercial work, drywall material is the easy part to price. Per 1,000 sq ft, USG puts finishing at about 370 LF of tape and 10 gallons of All Purpose compound, with about 2.7 lb of screws per 1,000 sq ft of board. Labor is where the price is made: hanging production depends on height, sheet size and openings; finishing production depends on the finish level in the spec, the number of corners and the amount of bead.

  • Board. Price per square foot of the board type (Type X, moisture-resistant, abuse-resistant), plus waste.
  • Finishing materials. Compound, tape, screws and bead at USG's rates. Add corner bead and trim as their own lines.
  • Labor. Square feet per crew-hour, hang and finish combined, or split them into two calculators for more control.
  • Finish level. Level 4 is common for painted walls; Level 5 adds a skim coat and changes both material and labor.
  • Height and access. Lifts and scaffolding reduce production and add equipment.
Price per square foot of board, not of floor. Drywall per square foot of building area depends on wall density. Keep the unit on board area.
Formula

Cost to sell price

VariableEffect
Level 5 finishMore compound and finishing labor
Ceilings and soffitsLower production than walls
Rated multi-layer wallsMore board and screws, less finishing per board sq ft
Heights over 12 ftLifts or scaffold, lower production
Curved wallsSpecialty board, slower
material / sq ft = board × (1 + waste) + 0.01 gal compound + 0.37 LF tape + 0.0027 lb screws (per sq ft) labor / sq ft = crew × wage × (1 + burden) ÷ sq ft per crew-hour sell / sq ft = (material + labor + equipment) × (1 + overhead) × (1 + profit)

Material rates from the USG Sheetrock installation and finishing guidance (J371). All prices, wages and production rates on load are placeholders.

Bid it by assembly

One price per partition type

The most defensible drywall bid gives one unit price per partition type on the partition schedule and applies it to the board area of that type. Ceilings, soffits and shaft walls get their own prices. That way an addendum that changes a wall type changes one line, not the whole bid.

RenderDraw's AI takeoff proposes partition lengths and board areas by type from plans and the partition schedule with the source sheet attached, so every unit price lands on a checked quantity.

Where RenderDraw fits

Wall lengths, ceiling areas and door counts, traceable.

RenderDraw's AI takeoff proposes partition lengths, ceiling areas and opening counts from plans, wall types and RCPs, each tied to its source, then routes uncertain items to estimator review.

  • Partition lengths by wall type. Linked to the plan and the wall-type legend.
  • Ceiling areas from the RCP. Kept by room and ceiling type.
  • Doors and openings counted. For deductions, frames and headers.
  • Estimator approval. Heights, waste, labor and margin stay with you.
Stack of gypsum drywall sheets with a T-square, utility knife, screw gun and joint compound
Honest by design

Send one interiors set

Plans, wall types and RCPs. Files stay private while RenderDraw assesses the request. No obligation.

RenderDraw does not publish accuracy percentages or time-saved claims. Test it on your own plan set.

FAQ

Questions estimators ask.

How do you calculate drywall cost per square foot?

Add board and finishing material per square foot to labor per square foot (crew cost per hour divided by production), add equipment, then apply overhead and profit.

How much compound and tape per square foot of drywall?

USG's guidance is about 370 LF of tape and 10 gallons of All Purpose compound per 1,000 sq ft of finished surface.

Why is drywall priced per square foot of board?

Board area is what the crew hangs and finishes. Floor area hides the amount of wall in the building.

Does finish level change the price?

Yes. Level 5 requires a skim coat over the whole surface, adding compound and labor compared with Level 4.

Can RenderDraw take off drywall?

RenderDraw's AI takeoff proposes partitions by type, ceilings and openings from drawings with sources and flags. Get a free sample takeoff.

Start small

Your price per foot, on footage you trust.

Send an interiors set. RenderDraw proposes board area by partition type with the source sheet, so your unit price is applied to checked quantities.

  1. Upload the plans, specs and schedules, plus an addendum if you have one.
  2. RenderDraw reviews the set and the scope you want tested.
  3. We follow up with extracted quantities, flagged items and next steps.

Book a meeting with RenderDraw

Bring your drawings, estimating process, or product configuration questions. Choose a time to talk with our team.

Prefer a separate window? Open the booking page.

Free sample takeoffCalculator